Demolition
Planned take-down of houses, farm buildings and commercial and industrial structures, at home in North Wales and on sites across the UK, with the arisings processed and the site left at an agreed level.
What this covers
- Full and partial demolition, domestic to industrial
- Mechanical take-down with shear and pulveriser attachments
- Soft strip and internal demolition
- Progressive and piece-small take-down on constrained sites
- Agricultural and farm building demolition
- Segregation, processing and removal of arisings
Demolition plan before mobilisation
Every demolition runs to a written plan, as CDM 2015 requires for demolition and structural dismantling: sequence of removal, temporary support and stability, exclusion zones, services isolated and proved dead, dust and noise control, and where the arisings go. You see it before we mobilise. If the structure behaves differently once it opens up, the revision is recorded rather than agreed on a nod.
Method to suit the structure
Mechanical take-down with shear and pulveriser attachments where there is room to work and drop material safely. Progressive, piece-small take-down where there is not: constrained sites, party walls, live premises and anything with a neighbour close by. Soft strip first where a building is going back to frame. Water suppression on the face, arisings kept in defined piles, haulage or on-site crushing planned rather than improvised.
Surveys and specialist works
Before a structure comes down we want the pre-construction information that goes with it: the surveys, drawings and service records the client or principal contractor holds. CDM 2015 puts those in their hands, and having them up front is what keeps a programme honest, because it is the difference between a price that holds and a price that moves once the building is open.
Where a survey identifies work for a licensed specialist, that specialist is brought in and completes their part before ours begins. If something unexpected shows up once the structure opens up, we stop, secure the area and tell you the same day.
Who the work is for
Main contractors and developers taking a demolition subcontract package, utilities and infrastructure clients, farms and estates, and private clients with a building to come down. The firm's own record includes substation decommissioning and bridge deck work alongside the domestic and agricultural jobs. A house take-down gets the same written plan as a commercial package, scaled to the job.
From our own sites
Structures coming down.
Photographs from our own demolition work, taken as the job happened.










Tell us what the job involves.
From small repairs and residential groundwork to demolition and complete site packages, speak to Cambrian about your project.